Completed
utility
Childress, TXFagus Substation
Utility substation foundations and equipment pads.

Project Stats
- Total Tonnage
- 42 T
- Number of Piers
- 131
Scope
Utility substation foundations and equipment pads.
Placed reinforcing steel for the Fagus electrical substation, including transformer pads, control house slab, and grounding mat foundations. Maintained close coordination with the utility's commissioning calendar.